The Department of Water and Sanitation has moved to clarify concerns surrounding the conclusion of employment contracts for workers employed on the Vlakfontein Canal Rehabilitation Project in Standerton, Mpumalanga. The department stresses that the process does not constitute retrenchments, but rather the natural conclusion of project-based contracts following the discontinuation of the project.
The Vlakfontein Canal Rehabilitation Project was launched in 2015 as a major infrastructure initiative aimed at improving water conveyance and irrigation systems in the area. The canal plays a critical role in supplying water to strategic users, including Eskom, Sasol and surrounding municipalities. At the start of the project, 241 local workers were employed, with the workforce standing at 178 employees by 2026.
Originally scheduled for completion within 48 months, the project experienced significant delays due to operational, technical and financial challenges. Following a comprehensive review of the project’s progress and long-term sustainability, the department decided to discontinue and de-establish the project.
According to the department, rehabilitation work on the canal could only be undertaken during scheduled dry periods while water supply was temporarily diverted through the Vaal River Eastern Sub-System. However, operational deficiencies within VRESAP have limited its reliability, making it difficult to shut down the canal for extended rehabilitation work without affecting water supply to key users. The department has indicated that the rehabilitation project may be revived once VRESAP becomes fully operational, and that consideration will be given to rehiring workers on a project-based basis at that stage.
The department says it engaged with organised labour and affected employees through the Departmental Bargaining Chamber regarding the discontinuation of the project and its implications. It maintains that the affected employees were always employed on contracts linked specifically to the lifespan of the project.
A total of 178 employees are affected, with their contracts set to end on 30 June 2026. As of 22 June 2026, 61 employees had acknowledged receipt of their termination letters.
24 Jun English South Africa Entertainment News · Music Interviews

Other recent episodes

In Conversation With Athlande Mathe, National Spokesperson

British‐Zimbabwean fugitive Ndodana Mkhanyisi Tshuma, accused of a triple murder in the United Kingdom, made his first appearance in the Johannesburg Magistrate’s Court on 13 July 2026. Tshuma is wanted in the UK for allegedly killing his wife, Nothabo Zandile Tshuma (42), and their daughters Natalie (15) and Nala (5)…
14 Jul 5 min

In Conversation With Owami Masango

Kurated Brand Biography Kurated is a proudly Black-owned South African haircare brand, founded in October 2023. Drawing inspiration from Ayurvedic, African, and Caribbean traditions, the brand creates products designed to nourish hair back to health, reduce breakage, and support growth. While Kurated places a special focus on textured hair, its…
14 Jul 7 min

In Conversation With Mpumelelo Zikalala, Legal Expert

Vusimuzi “Cat” Matlala, an alleged underworld figure, is at the center of a major corruption case involving a R228‐million SAPS tender linked to Medicare24. He had pleaded guilty to seven counts of fraud, corruption, and money laundering, and entered into a plea deal with the state that proposed an eight‐year…
14 Jul 3 min

In Conversation With Goodenough Mashego- political analyst

The Madlanga Commission of Inquiry enters another critical phase this week as it turns its attention to the Investigating Directorate Against Corruption (IDAC)—the specialised unit within the National Prosecuting Authority responsible for investigating and prosecuting complex corruption and state capture-related crimes. The Commission was established by President Cyril Ramaphosa in…
13 Jul 1 hour

In Conversation With JMPD Spokesperson, Xolani Fihla

The Johannesburg Metropolitan Police Department (JMPD) has issued a public safety advisory after its primary emergency call-taking and dispatch line became temporarily unavailable due to a technical fault. According to the department, the disruption has been intermittent since Friday, 10 July, affecting the main emergency number 011 375 5918. Technicians…
13 Jul 5 min